Planned works will see the installation of temporary bridge props installed adjacent to the main bridge piers at several locations below the bridge deck, in preparation for a permanent repair. Pre-construction work and investigations commenced on Friday 12th March 2021.

To ensure the safety of road workers and the travelling public, speed and lane restrictions will be in place on the M8 for the full extent of these structures; and associated eastbound slip roads at Junctions 17 and Junction 18 and westbound slip roads at Junction 15 on slip and Junction 17 off slip will be closed. Slip roads at Junction 16 remain open. Signed diversion routes are in operation.

Narrowed lanes have been introduced on the mainline of the M8 through the structures. HGVs are being encouraged to consider using an alternative route due to these narrow sections.

Road users are advised to plan ahead and allow extra time to complete their journey. We thank the travelling public, stakeholders, residents, and businesses, who are impacted for their patience while this essential refurbishment work takes place.

MOTORWAY DIVERSIONS

Motorway Diversion Routes

  • Eastbound Junction 18 on slip diversion: Traffic will travel on the A804 St Georges Road to Phoenix Road, Dobbie’s Loan to the Junction 16 eastbound on slip road.
  • Eastbound Great Western Road on slip diversion: Traffic will travel via West Graham Street to Garscube Road then onto Dobbie’s Loan to Junction 16 eastbound on slip road.
  • Westbound Junction 15 on slip road diversion: Traffic will travel via Springburn Road, Royston Road, A804 Baird Street, Dobbie’s Loan, Phoenix Road and then re-join at Junction 17 Westbound.
  • Westbound Junction 17 off slip diversion: Traffic will travel via the Junction 19 off slip road to Argyle Street to North Street and follow signage.

NEWS ARCHIVE

 

MOTORWAY DIVERSIONS

MOTORWAY TRAFFIC MANAGEMENT

Motorway Diversion Routes

  • Eastbound Great Western Road on slip diversion: Traffic will travel via West Graham Street to Garscube Road then onto Dobbie’s Loan to Junction 16 eastbound on slip road.

  • Westbound Junction 15 on slip road diversion: Traffic will travel via Springburn Road, Royston Road, A804 Baird Street, Dobbie’s Loan, Phoenix Road and then re-join at Junction 17 Westbound.

  • Westbound Junction 17 off slip diversion: Traffic will travel via the Junction 19 off slip road to Argyle Street to North Street and follow signage.

AUGUST 2024

M8 WOODSIDE VIADUCTS: PACKAGE OF ESSENTIAL OVERNIGHT CLOSURES ON M8 JUNCTIONS 19 TO 15 COMMENCE SUNDAY 11th AUGUST 2024

Amey, on behalf of Transport Scotland, is undertaking a package of essential overnight maintenance on the eastbound M8 between Junctions 18 (Charing X) and 16 (Craighall) which will be carried out in multiple phases throughout 2024.

The next phase of the eastbound works will take place from Sunday 11th August until Friday 6th September 2024, from 10pm until 6am, each night, excluding Friday nights and Saturdays.

This scheme is to enable the next phase of works of the M8 Woodside Viaducts Junctions 16-17.

Work will be carried out using overnight closures only, excluding Friday nights and Saturdays, with signed diversion routes in operation.

M8 Eastbound closure traffic will be directed off at junction 18 (St George’s Road) onto northbound St George’s Road. Traffic will then follow the diversion onto southbound Garscube Road for Dobbie’s Loan and back onto junction 16 (Craighall).

Access for emergency service vehicles will not be maintained throughout these works.

Please plan your journey and allow extra time for travel through the signed diversion.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

JUNE 2024

M8 WOODSIDE VIADUCTS: PACKAGE OF ESSENTIAL OVERNIGHT CLOSURES ON M8 JUNCTIONS 19 TO 15 COMMENCE SUNDAY 23rd JUNE 2024

EXTENDED

These works have been extended by one week and will now finish on Friday 9th August 2024 at 6am.

Amey, on behalf of Transport Scotland, is undertaking a package of essential overnight closures on the westbound M8 between Junctions 18 (Charing X) and 16 (Craighall) which will be carried out in multiple phases throughout 2024.

Phase Two of the westbound works will take place from Sunday 23rd June until Friday 9th August 2024, from 10pm until 6am, each night, excluding Friday and Saturday nights.

This scheme is to enable the next phase of works of the M8 Woodside Viaducts Junctions 16-17.

Work will be carried out using overnight closures only, excluding Friday and Saturday nights, with signed diversion routes in operation.

Westbound traffic will exit at M8 Junction 16 (Craighall) onto the westbound Dobbie’s Loan and join Garscube Road. From here, traffic will be directed to West Graham Street to re-join the M8 at Junction 17.

The junction 15 loop on-slip from A803 southbound is also closed. Traffic will be diverted via Castle Street, onto Cathedral Street and join North Hanover Street for Cowcaddens road where traffic will then join the mainline diversion at Cowcaddens X.

Access for emergency service vehicles will not be maintained throughout these works.

Please Note: Closure timings have been co-ordinated with bus services using the route, to maintain the regular service.

Please be conscious of other works across the M8 corridor through Glasgow when planning your journey and allow extra time for travel through the signed diversions.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

JUNE 2024

M8 WOODSIDE VIADUCTS: ROAD REALIGNMENT ON THE A81 GARSCUBE ROAD COMMENCE SATURDAY 15TH JUNE 2024

Amey, on behalf of Transport Scotland, is implementing road realignment on the northbound A81 Garscube Road from Saturday 15th June. 

This involves a continuous closure of the east side of the roundabout to allow the propping of the M8 Woodside Viaduct. Traffic will follow a signed single lane contraflow in both directions on the west side of the roundabout. 

Access for emergency service vehicles will be maintained throughout these works. 

 

 

MAY 2024

M8 WOODSIDE VIADUCTS: ESSENTIAL MAINTENANCE COMMENCES TUESDAY 28TH MAY 2024

Two essential maintenance schemes will commence on the M8 Woodside Viaducts J16-J17 project on Tuesday 28th May.

Scheme One: works on the eastbound M8 carriageway at M8 Woodside Viaducts.

Scheme Two: works on A81 Garscube Road and the A804 Dobbie’s Loan.

Full details of these schemes are outlined below:

Scheme One - M8 EB

PACKAGE OF ESSENTIAL OVERNIGHT WORKS ON EASTBOUND M8 JUNCTIONS 19 TO 15 COMMENCE TUESDAY 28TH MAY 2024

Amey, on behalf of Transport Scotland, is undertaking a package of essential overnight maintenance on the eastbound M8 between Junctions 18 (Charing X) and 16 (Craighall) which will be carried out in multiple phases throughout 2024. These overnight closures will run Sunday to Friday only until Friday 21st June 2024.

Phase Four of the eastbound works will take place from Tuesday 28th May until Friday 21st June 2024, from 10pm until 6am, each night, excluding Friday nights and Saturdays.

This scheme is to enable the next phase of works of the M8 Woodside Viaducts Junctions 16-17.

Work will be carried out using overnight closures only, excluding Friday nights and Saturdays, with signed diversion routes in operation.

Mainline M8 eastbound traffic will be taken off at junction 18 (St George’s Road) and travel northbound on St George’s Road. Traffic will then follow the diversion southbound onto Garscube Road, heading eastbound onto Dobbie's Loan and back on at junction 16 (Craighall).

On Slip Closure Diversion

The eastbound junction 19 (Anderston) and junction 18 (Charing X) on slip closure traffic will be diverted northbound to North Street onto St George’s Road where it will then join the mainline diversion to junction 16.

COMPLETE - Scheme Two - Garscube Road and Dobbie’s Loan

RESURFACING AND RELINING ON THE A81 GARSCUBE ROAD AND A804 DOBBIE’S LOAN WESTBOUND COMMENCE TUESDAY 28TH MAY 2024

Amey, on behalf of Transport Scotland, is undertaking essential maintenance on the northbound and southbound A81 Garscube Road at Garscube Roundabout and westbound A804 Dobbie’s Loan from Tuesday 28th May until Friday 7th June 2024, from 8am to 8pm, excluding weekends.

The work will be carried out using weekday closures, with signed diversion routes in operation.

Phase 1 – 28th – 31st May

Garscube Road Northbound Traffic Diversion

Traffic will be diverted west along West Graham Street, taking the exit for junction 17 before exiting at Charing Cross. Turn right onto North Street and continue north onto St. George’s Road. Continue to follow for Garscube Road where the diversion ends.

Dobbie’s Loan Westbound Traffic Diversion

Traffic will turn left onto Garscube Road and drive southbound. From here, traffic will turn right onto West Graham Street where they will then follow the Garscube Road northbound diversion outlined above.

 

Phase 2 - 3rd – 4th June

Garscube Road Northbound

Traffic will follow the same diversion as outlined in the Garscube Road northbound diversion above.

Dobbie’s Loan Westbound

Traffic will turn left onto Port Dundas Road and travel south. From here, traffic will turn right onto Cowcaddens Road, and then straight onto West Graham Street westbound. Traffic will then follow the Garscube Road northbound diversion outlined above.

 

Phase 3 – 4th – 5th June

Dobbie’s Loan Westbound

Traffic will turn left onto Port Dundas Road and then travel south before turning right onto Cowcaddens Road. From here, traffic will turn right onto the Garscube Road northbound diversion outlined above.

 

Phase 4 – 5th – 7th June

Garscube Road Southbound Traffic Diversion

Traffic will turn onto St. George’s Road, travelling southbound before being diverted left through Charing Cross. Traffic will then turn left onto Sauchiehall Street, before taking another left onto Rose Street. Traffic will then be diverted right onto Renfrew Street and then left onto Hope Street where the diversion ends at Cowcaddens Road.

 

Bus Diversions

Bus routes and bus stops will also have temporary changes during this time as outlined below:

7 7A and 75 Service

These services will use Cowcaddens Road, Port Dundas, Dobbies Loan and Craighall Road. 

60, 60A ,61 and M3 Services

These services will be diverted via Bath Street, West Graham Street, Great Western Road, Napiershall Street to Maryhill Road.

 

Access for emergency service vehicles will not be maintained throughout these works.

Please plan your journey and allow extra time for travel through the signed diversion.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

MARCH 2024

M8 WOODSIDE VIADUCTS: PACKAGE OF ESSENTIAL OVERNIGHT WORKS ON M8 JUNCTIONS 19 TO 15 COMMENCE SUNDAY 17th MARCH 2024 

Amey, on behalf of Transport Scotland, is undertaking a package of essential overnight maintenance on the eastbound M8 between Junctions 19 and 15 and westbound M8 between Junctions 16 and 18, which will be carried out in multiple phases throughout 2024. Each set of overnight closures will alternate between carriageways and run Sunday to Friday only. 

Eastbound Closures

Closures will start with Phase Two of the eastbound works which will take place between Sunday 17th March and Friday 10th May 2024 from 10pm until 6am, each night, excluding weekend nights.

This scheme is to enable the next phase of works of the M8 Woodside Viaducts.

Eastbound work will be carried out using overnight closures only, Sunday to Friday, on the following dates:

17th March – 22nd March

24th March – 29th March

7th April – 12th April

28th April – 3rd May

5th May – 10th May

Signed diversion routes will be in operation.

  • Eastbound M8 traffic will be directed off the M8 at Junction 18 (St George’s Road) onto St George’s Road, following to Garscube Road, onto Dobbie’s Loan, then back onto the M8 at Junction 16 (Craighall).
  • There will be eastbound slip road closures at Junctions 19 and 18 (Charing X), with traffic being directed to North Street and then St George’s Road to join the main diversion, as outlined above.

Westbound Closure

Phase One of westbound works will then take place between Sunday 31st March and Friday 24th May 2024 from 10pm until 6am, each night, excluding weekend nights.

Westbound work will be carried out using overnight closures only, Sunday to Friday, on the following dates:

31st March – 5th April

14th April – 19th April

21st April – 26th April

12th May – 17th May

19th May – 24th May

Signed diversion routes will be in operation.

  • Traffic will exit the M8 at junction 16 (Craighall), following the diversion westbound to Dobbie's Loan. Traffic will then drive southbound on Garscube Road, approaching westbound West Graham Street before joining back onto the M8 westbound via junction 17 westbound on-slip.

Access for emergency service vehicles will not be maintained throughout these works.

Please plan your journey and allow extra time for travel through the signed diversion.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

M8 WOODSIDE VIADUCTS: WORKS ON A81 GARSCUBE ROAD AND A804 DOBBIE'S LOAN COMMENCE TUESDAY 26TH MARCH 2024

UPDATE 05.04.24: These works have now finished.

Amey, on behalf of Transport Scotland, is undertaking essential maintenance on the northbound A81 Garscube Road at Garscube Roundabout and westbound A804 Dobbie’s Loan from Tuesday 26th March until Saturday 6th April 2024; from 12:15am until 6am, each night.

The work will be carried out using weeknight closures only with signed diversion routes in operation.

Northbound traffic will be diverted at Cowcaddens Cross along West Graham Street and Great Western Road and on to Napiershall Street.

Westbound Dobbie’s Loan traffic will be diverted at Port Dundas Street onto Cowcaddens Road where they will then follow the northbound diversion.

Glasgow City Council Cambridge Street northbound closure – Renfrew Street/Hope Street and back onto Cowcaddens Road, westbound traffic at that point will follow the Garscube northbound closure diversion, and traffic wanting to access junction 16 eastbound on slip will be directed via Port Dundas Road/Dobbie’s Loan.

Access for emergency service vehicles will not be maintained throughout these works.

Please Note: Closure timings have been co-ordinated with bus services using the route, to maintain the regular service.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

JANUARY 2024

EXTENDED

Please be advised that M8 eastbound junctions 18 to 16 overnight works have been extended and will now end on Friday 15th March 2024. We apologise for any inconvenience this may cause.

M8 WOODSIDE VIADUCTS: PACKAGE OF ESSENTIAL WORKS ON M8 JUNCTIONS 18 TO 16 EASTBOUND COMMENCE SUNDAY 28th JANUARY 2024

Amey, on behalf of Transport Scotland, is undertaking a package of essential overnight maintenance on the eastbound M8 between Junctions 18 and 16, which will be carried out in multiple phases throughout 2024. 

Phase One will take place from Sunday 28th January until Saturday 9th March 2024 from 8pm* until 6am, each night. *Subject to traffic volumes. 

This scheme is to enable the next phase of repair of the M8 Woodside Viaducts Junctions 16-17. 

The work will be carried out using weeknight closures only with signed diversion routes in operation.  

  • Eastbound M8 traffic will be directed off the M8 at Junction 18 onto St George’s Road, following to Garscube Road, onto Dobbie’s Loan, then back onto the M8 at Junction 16 (Craighall). 
  • There will be eastbound slip road closures at Junctions 19 and 18, with traffic being directed to North Street and then St George’s Road to join the main diversion, as outlined above. 

Access for emergency service vehicles will not be maintained throughout these works. 

Please plan your journey and allow extra time for travel through the signed diversion. 

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route. 

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable. 

POSTPONED

M8 WOODSIDE VIADUCTS: WORKS ON A81 GARSCUBE ROAD COMMENCE TUESDAY 30th JANUARY 2024

Amey, on behalf of Transport Scotland, is undertaking essential overnight maintenance on the northbound A81 Garscube Road at Garscube Roundabout, from Tuesday 30th January until Wednesday 14th February 2024; from midnight until 6am, each night.

The work will be carried out using weeknight closures only, with signed diversion routes in operation.

Northbound traffic will be diverted at Cowcaddens Cross along West Graham Street and Great Western Road and on to Napiershall Street.

Westbound Dobbie’s Loan traffic will be diverted at Port Dundas Street onto Cowcaddens Road where they will then follow the northbound diversion.

Glasgow City Council will also have a northbound closure on Cambridge Street, with eastbound M8 traffic diverted to Cowcaddens Road onto Port Dundas Road for Dobbie’s Loan eastbound

Access for emergency service vehicles will not be maintained throughout these works.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

NOVEMBER 2023

M8 WOODSIDE VIADUCTS: PACKAGE OF ESSENTIAL MAINTENANCE ON THE M8 EASTBOUND BETWEEN JUNCTIONS 25 AND 12 CONTINUES WITH PHASE 3 COMMENCING THURSDAY 23RD NOVEMBER 2023

Amey, on behalf of Transport Scotland, are undertaking a package of essential maintenance on the M8 eastbound between Junctions 25 and 12, which will be carried out in multiple phases in the months of November and December 2023.

UPDATE Dec. 23

The inclusion of a total closure of the M8 junction 16 eastbound on slip will now continue
until completion of phase three on Thursday 21st December.

The work will be carried out with signed diversions in operation as follows:


Traffic will exit at junction 18 (St Georges Road) onto St Georges Road for Garscube Road.
Traffic will then continue to Dobbie’s Loan. Traffic will then be diverted onto Kyle Street
following to Baird Street and onto Castle Street. From here, traffic will then rejoin the M8
eastbound via the junction 15 eastbound on slip, where the diversion will end.

UPDATE Nov. 23

Phase Three will now incorporate a total closure of the M8 junction 16 eastbound on slip from Monday 4th December until Wednesday 13th December 2023.

Diversion Routes from 4th December until 13th December:

Diversion: Traffic will exit at junction 18 (St Georges Road) onto St Georges Road for Garscube Road. Traffic will then continue to Dobbie’s Loan. Traffic will then be diverted onto Kyle Street following to Baird Street and onto Castle Street. From here, traffic will then rejoin the M8 eastbound via the junction 15 eastbound on slip, where the diversion will end.

Phase Three will take place from Thursday 23rd November until Thursday 21st December 2023.

This scheme will benefit around 74,000 vehicles using this route each day, by improving the condition of the carriageway and its structures, reducing the need for more extensive maintenance in the future.

The work will be carried out using overnight road closures with signed diversions in operation.

Phase Three: Closure of the eastbound M8 carriageway between Junctions 18 and 16 and the eastbound on slips at junction 19 and junction 18. This will begin on Thursday 23rd November until Thursday 30th November 2023, starting at 10pm each night with the traffic management removed by 6am the following morning. The same section of carriageway and slip roads will be closed again on Sunday 3rd December until Thursday 21st December 2023, starting at 10pm each night with the traffic management removed by 6am the following morning.

Diversions for this phase will operate as follows:

Diversion: Traffic will exit at junction 18 (St Georges Road) onto St Georges Road for Garscube Road. Traffic will then continue to Dobbie’s Loan onto junction 16 (Craighall).

Slip Road Diversions: Traffic will be diverted for North Street onto St Georges Road and then join the diversion for the main closure.

Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles that deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be identified away from the agreed diversion route.

There will be controlled access for emergency vehicles determined on site by the type of work taking place each evening.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

Future phases will be communicated in due course. Road users are advised to allow extra time for any journeys throughout this period and we thank you for your continued patience and co-operation while this essential work takes place.

 

DECEMBER 2023

M8 WOODSIDE VIADUCTS: ESSENTIAL WORKS ON THE A804 DOBBIE'S LOAN EASTBOUND COMMENCES FRIDAY 1ST DECEMBER 2023

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South-West Trunk Road Unit, are undertaking essential works on the A804 Dobbie’s Loan eastbound, from Friday 1st December until Sunday 3rd December 2023, from 8pm until 6am, each night.

The work will be carried out using overnight closures with signed diversion routes in operation.

Eastbound traffic will be diverted via A81 Garscube Road southbound onto Cowcaddens Road travelling to Port Dundas Road and finishing on Dobbie's Loan.

Access for emergency service vehicles will not be maintained throughout these works.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

NOVEMBER 2023

M8 WOODSIDE VIADUCTS: WORKS ON A804 DOBBIE'S LOAN WESTBOUND AND A81 GARSCUBE ROAD SOUTHBOUND COMMENCE MONDAY 20TH NOVEMBER 2023

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South-West Trunk Road Unit, are undertaking essential maintenance on the A81 Garscube Roundabout southbound and A804 Dobbie’s Loan westbound. Works will begin on Monday 20th November until Thursday 23rd November, from 8pm until 6am, each night.

The work will be carried out using overnight closures with signed diversion routes in operation.

The closure of A81 Garscube Road southbound then spans from the A804 Dobbie’s Loan to Cowcaddens Road. The closure of A804 Dobbie’s Loan westbound begins at Port Dundas Road to A81 Garscube Road.

A81 Garscube Road southbound traffic will be diverted via A804 Dobbie’s Loan eastbound onto Port Dundas Road finishing on Cowcaddens Road.

A804 Dobbie’s Loan westbound traffic will be diverted via Port Dundas Road onto Cowcaddens Road for Garscube Road northbound.

Access for emergency service vehicles will not be maintained throughout these works.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

 

OCTOBER 2023

M8 WOODSIDE VIADUCTS: PHASED WORKS ON A804 DOBBIE'S LOAN COMMENCE FRIDAY 6TH OCTBER 2023

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South-West Trunk Road Unit, are undertaking phase two of works on the A804 Dobbie’s Loan eastbound, between A81 Garscube Roundabout and Port Dundas Road, from Friday 6th October at 8pm until Monday 9th October at 6am.   

The work will be carried out using a continuous closure with signed diversion routes in operation. 

A804 Dobbie’s Loan eastbound traffic will be diverted to Cowcaddens Road and then onto Port Dundas Road. 

Access for emergency service vehicles will not be maintained throughout these works. 

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route. 

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.  

SEPTEMBER 2023

M8 WOODSIDE VIADUCTS: PHASED WORKS ON A81 GARSCUBE ROAD AND A804 DOBBIE'S LOAN COMMENCE TUESDAY 26TH SEPTEMBER 2023

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South-West Trunk Road Unit, are undertaking phase one of works on the A81 Garscube Road southbound, between Garscube Roundabout and Cowcaddens Road, and the A804 Dobbie’s Loan westbound, between Port Dundas Road and A81 Garscube Roundabout, from Tuesday 26th September until Sunday 1st October 2023, between 10pm and 6am, each night.

The work will be carried out using a continuous closure with signed diversion routes in operation.

A81 Garscube Road southbound traffic will be diverted to the A804 Dobbie’s Loan onto Port Dundas Road and then Cowcaddens Road.

A804 Dobbie’s Loan westbound traffic will be diverted to Port Dundas Road onto Cowcaddens Road and then Garscube Road.

Access for emergency service vehicles will not be maintained throughout these works.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

AUGUST 2023

M8 WOODSIDE VIADUCTS: ENABLING WORKS ON THE M8 EASTBOUND, JUNCTIONS 19 to 16 COMMENCE MONDAY 21st AUGUST

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South-West Trunk Road Unit, are undertaking enabling works on the M8 eastbound, at junction 19 to 16, from Monday 21st August until Thursday 31st August 2023, between the hours of 10pm and 6am, each night. 

The work will be carried out using overnight closures with signed diversion routes in operation. 

Eastbound traffic will be directed to leave the motorway at junction 18 St George’s Road/ Great Western Road. Traffic will then follow diversions onto St George’s Cross, then St George’s Road, onto Garscube Road. They will then continue onto Dobbie’s Loan, before re-entering the M8 eastbound at junction 16 Craighall. 

The junction 19 on-slip at Anderson and the junction 18 on-slip at Charing Cross will also be closed. Traffic looking to join the M8 eastbound will be directed via North Street or St George’s Road and joining the diversion route at junction 18. 

Please note: Access for emergency service vehicles via the M8 between eastbound junctions 19 to 16 will not be maintained throughout these works. 

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route. 

All schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.  

M8 EASTBOUND JUNCTIONS 18-15:

UPDATE - REOPENED

The works outlined below are now complete, therefore, the M8 eastbound junctions 18 to 15 overnight closures are now finished.

M8 WOODSIDE VIADUCTS:

ESSENTIAL MAINTENANCE ON THE M8 EASTBOUND, AT JUNCTIONS 18 to 15, COMMENCES SATURDAY 15th JULY

Amey, on behalf of Transport Scotland, are undertaking the latest phase of overnight maintenance on the M8 eastbound, between Junction 18 and Junction 15, from Saturday 15th July until Friday 28th July 2023. Work will take place between the hours of 10pm and 6am.

The work will be carried out using a series of overnight road closures, with a signed diversion route in operation.

Eastbound traffic will exit the M8 at Junction 19, Bothwell Street and will follow diversion signage to Pitt Street, St Vincent Street and onto North Street. From here, vehicles will continue to St Georges Road and Garscube Road before the diversion ends at Dobbie’s Loan. Traffic will then return to the eastbound M8 via Junction 16, Craighall.

PLEASE NOTE: Access for emergency service vehicles via the M8 between eastbound Junctions 18 to 15 will not be maintained throughout these works.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

All schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

MARCH 2023

UPDATE - CLOSURES EXTENDED

Due to operational requirements, the works outlined below have been extended and are now scheduled to end on Saturday 22nd July 2023.

M8 WOODSIDE VIADUCTS:
WORKS ON M8 JUNCTION 17 

Amey, on behalf of Transport Scotland, is undertaking carriageway realignment works on the M8 junction 17 on-slip and are due to complete on Saturday 22nd July 2023.

The works on the M8 westbound on-slip at Junction 17 (West Graham Street) are using a full continuous closure of the slip road, with signed diversion routes in operation.

Further works will begin on the Cowcaddens junction from Monday 17th July until Friday 21st July 2023, using a full continuous closure of the junction, with signed diversion routes in operation.

This scheme will provide alternative access to the westbound M8 as part of the ongoing repair work being undertaken on the M8 Woodside Viaducts Junctions 16 - 17.

M8 Westbound Junction 17 On-Slip Diversion: Traffic will be diverted at West Graham Street, travelling eastbound to Cowcaddens. From here, vehicles will continue to Garscube Roundabout and join the A804 Phoenix Road, before taking the westbound M8 on-slip.

Cowcaddens Junction Diversion: Traffic will be diverted via local roads.

Eastbound traffic travelling from West Graham Street for Cowcaddens Road will be diverted via Garscube Road onto Dobbie's Loan continuing onto Port Dundas Road or North Hanover Street.

Southbound traffic travelling from Garscube Road for Cowcaddens Road will be diverted via Dobbie's Loan.

Westbound traffic travelling from Cowcaddens Road to Garscube Road will be diverted via North Hanover Street and Dobbie's Loan.

Access for emergency service vehicles will not be maintained throughout these works.

These works will be subject to the completion of traffic signal upgrades on the local road network.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

All schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

JUNE 2023

UPDATE: PLANNED MAINTENANCE POSTPONED

Due to operational requirements, planned maintenance on the A804 Phoenix Road from Monday 19th June until Wednesday 21st June 2023 has been postponed. We apologise for any inconvenience this may cause.

This work is now scheduled to take place on the A804 Phoenix Road from Thursday 6th July until Friday 7th July, between the hours of 8pm and 6am.

These works will also require a closure of the M8 eastbound junctions 19 to 16 from Thursday 6th July until Friday 7th July, between the hours of 10pm and 6am.

The work will be carried out using overnight road closures, with signed diversion routes in operation.

Phoenix Road Diversion:

Eastbound traffic will be directed to St Georges Road, onto Garscube Road then onto Dobbies Loan, before joining the M8 junction 16 eastbound.

Westbound traffic will be directed to North Street, onto Charing Cross then onto Newton Street, before joining the M8 junction 19 westbound.

M8 Eastbound Diversion:

M8 eastbound traffic will be directed off at junction 19 Bothwell then onto Pitt Street, followed by North Street and onto St Georges Road. Traffic will then follow the diversion route onto Garscube Road for Dobbies Loan and back onto the M8 eastbound junction 16 Craighall.

PLEASE NOTE: Vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times. Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

PLEASE NOTE: Access for emergency service vehicles will not be maintained throughout these works.

M8 WOODSIDE VIADUCTS:

ESSENTIAL MAINTENANCE ON THE A804 PHOENIX ROAD COMMENCES MONDAY 19TH JUNE - POSTPONED

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South-West Trunk Road Unit, are undertaking essential maintenance on the A804 Phoenix Road from Monday 19th June until Wednesday 21st June 2023, between the hours of 8pm and 6am, each night.

The work will be carried out using overnight road closures, with signed diversion routes in operation.

Eastbound traffic will be directed to St Georges Road, onto Garscube Road then onto Dobbies Loan, before joining the M8 junction 16 eastbound.

Westbound traffic will be directed to North Street, onto Charing Cross then onto Newton Street, before joining the M8 junction 19 westbound.

PLEASE NOTE: vehicles entering the LEZ as part of the diversion must follow the diversion signage at all times.  Any vehicles which deviate from the published diversion route may be issued with penalty charge notice(s) from Glasgow City Council should they be captured out with the agreed diversion route.

PLEASE NOTE: Access for emergency service vehicles will not be maintained throughout these works.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

 

APRIL 2023

M8 WOODSIDE VIADUCTS:

WORKS ON A804 PHOENIX ROAD COMMENCE 24th APRIL

Amey, on behalf of Transport Scotland, is undertaking overnight works on the westbound A804 at Phoenix Road as part of the M8 Woodside Viaduct project. The work will take place during fifteen weeknight closures, spread across three weeks. Work will begin on Monday 24th April and continue until Saturday 13th May 2023.

Signed diversion routes will be in operation between 8 pm and 6 am each night.

Traffic will be diverted at Garscube Roundabout. Northbound traffic will join Garscube Road and then travel south on St Georges Road. Southbound traffic will be diverted at Garscube Roundabout to join Cowcaddens Road and from here will travel through Port Dundas Road, Dobbies Loan, and Garscube Road. Traffic will then follow the westbound diversion detailed below.

M8 westbound traffic will follow existing signage on-site via North Street, Charing Cross, Newton Street then onto the westbound on-slip road at Junction 19.

PLEASE NOTE: Access for emergency service vehicles will not be maintained throughout these works.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

The diversion route is illustrated below.

APRIL 2023
WORKS ON GARSCUBE ROUNDABOUT COMMENCE 3rd APRIL

Amey, on behalf of Transport Scotland, will be undertaking works on the northbound A81 at Garscube Roundabout as part of ongoing maintenance on the M8 Woodside Viaducts. The works, which involve the installation of a temporary propping system, will take place using ten weeknight overnight closures, from Monday 3rd April until Saturday 15th April 2023, from midnight until 6am, each night.

The work will be carried out using nighttime road closures, with a signed diversion route in operation.

Due to the no-right-turn at St Georges Road from A804 Phoenix Road westbound, the signed diversion will direct traffic via the A804 Phoenix Road westbound to St Georges Cross then left onto North Street southbound and Charing Cross.

Eastbound M8 traffic will be directed to use M8 Junction 18.

Local northbound traffic will be directed to return onto North Street / St Georges Road until the junction at A81 Garscube Road, where the diversion will end.

Local traffic may utilise Maryhill Road to travel northbound. Those intending to travel eastbound may utilise Maryhill Road and Hinshaw Street.

PLEASE NOTE: Access for emergency service vehicles will not be maintained throughout these works.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

MARCH 2023
WORKS ON A804 PHOENIX ROAD COMMENCE 27th MARCH

Amey, on behalf of Transport Scotland, is undertaking overnight works on the crossheads and the propping system of the M8 Woodside Viaducts at the westbound A804 Phoenix Road. The work will take place using five overnight closures. Work will begin on Monday 27th March until Saturday 1st April 2023, between 8pm and 6am, each night.

This scheme will be carried out using overnight road closures, with signed diversion routes in operation.

Traffic will be diverted at Garscube Roundabout. Northbound traffic will join Garscube Road and then travel south on St Georges Road. Southbound traffic will be diverted at Garscube Roundabout to join Cowcaddens Road and from here will travel through Port Dundas Road, Dobbies Loan, and Garscube Road. Traffic will then follow the below northbound diversion.

M8 westbound traffic will follow existing signage on site via North Street, Charing Cross, Newton Street then onto the westbound on-slip road at Junction 19.

PLEASE NOTE: Access for emergency service vehicles will not be maintained throughout these works.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

NOVEMBER 2022

FROM: NOVEMBER 28th

M8 WOODSIDE VIADUCTS INVESTIGATION WORKS COMMENCE MONDAY 28TH NOVEMBER 2022

Amey, on behalf of Transport Scotland, are undertaking essential overnight investigation works as part of the M8 Woodside Viaducts repair scheme. These require closures of the A82 Great Western Road flyover between St George’s Cross Underground station and the Junction 17 on-slip of the M8 westbound at Stow College - and lane restrictions at the Cowcaddens Road/West Graham Street junction - from Monday 28th November until Friday 2nd December 2022, between the hours of 10pm and 6am, each night.

These investigations will inform future stages of work on the M8 Woodside Viaducts. The work will be carried out in phases, initially using a full overnight closure of the eastbound and westbound Great Western Road, with a signed diversion route in operation.

Eastbound traffic will be directed to leave Great Western Road via Maryhill Road and will join St George’s Road before continuing on to Garscube Road. From here, traffic will use the Cowcaddens Road/West Graham Street junction to continue their journey eastbound.

The second phase of the works requires a closure on the straight-ahead lane from Cowcaddens Road to West Graham Street. While this is in place, traffic will be directed north on Garscube Road and will then travel west on A804 Phoenix Road and then north on Maryhill Road to return to Great Western Road via Napiershall Street. At the same time, the Rose Street entrance to Cowcaddens Junction will also be closed, with traffic being diverted via Buccleuch Street, Dallhousie Street and Renfrew Street to then continue their journey via Cambridge Street.

Depending on the progress of the initial phase, the second phase is likely to commence for three nights from either Wednesday 30th November or Thursday 1st December 2022. At times during this phase there will be lane restrictions in force on the Cowcaddens Road/West Graham Street junction, but traffic will still be able to travel through without the need for a further diversion.

We thank road users for their patience and co-operation while these essential investigation work takes place.

Access for emergency service vehicles will be maintained throughout these works.

OCTOBER 2022

FROM: OCTOBER 17th

M8 WOODSIDE VIADUCTS: NEXT PHASE OF PROPPING WORKS ON A804 PHOENIX ROAD

Amey, on behalf of Transport Scotland, are undertaking the next phase of propping works on the M8 Woodside Viaducts on the A804 Phoenix Road, directly below the Viaducts from Monday 17th October 2022.

Phoenix Road will be closed eastbound to facilitate the next phase of propping to the eastbound viaduct at two locations adjacent to Phoenix Road, and will remain in place until work at this location is completed.

The initial work will allow the completion of groundworks to facilitate the propping installation at the eastbound bridge supports. This will allow completion of ongoing repair works. The works will extend onto the carriageway there is no other safe option for vehicles to pass.

A signed diversion route will be in operation while this work is taking place.

Eastbound traffic intending to use the eastbound A804 Phoenix Road will be directed on to St George’s Road and then Garscube Road.

Vehicles will still be able to access the westbound M8 on-slip road via Phoenix Road, and the westbound A804 is unaffected by this closure.

Please note, emergency service vehicles will also be required to use the diversion route.

OCTOBER 2022

FROM: OCTOBER 31

M8 WOODSIDE VIADUCTS: OVERNIGHT RESURFACING WORK COMMENCES 31ST OCTOBER 

Amey, on behalf of Transport Scotland, are undertaking resurfacing and lining work on the westbound M8 Woodside Viaducts main line and its off-slip roads, between Junction 17 and Junction 19, from Monday 31st October until Wednesday 2nd November 2022. The work will take place between 8pm to 6am, each night. 

This scheme requires a full closure of the westbound M8 carriageway for the extent of the works, with a signed diversion in operation. 

Westbound traffic will be directed to leave the M8 at Junction 16 to join the A804 and from here travel to M8 Junction 19 via A804 Dobbies Loan, Newton Street and A814 Argyle Street before re-joining the M8 Westbound at Jct 19 where the diversion will end. 

Local traffic at Jct 15 intending to travel Westbound on the M8 will also be diverted through local roads to join with traffic taken off Jct 16 at Dobbies Loan.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable. 

FROM: OCTOBER 17th

M8 WOODSIDE VIADUCTS: OVERNIGHT MAINTENANCE AT A804 DOBBIES LOAN

Amey, on behalf of Transport Scotland, are undertaking essential overnight maintenance on the M8 Woodside Viaducts beneath the structure on the eastbound A804 Dobbies Loan and the westbound A81 between Garscube Road and Port Dundas Road, from Monday 17th October to Friday 21st October 2022. The work will take place between 8pm and 6am, each night and the road will re-open as normal outwith these times.

This scheme requires a full closure of the road for the extent of the works, with a signed diversion in operation.

Eastbound traffic will be directed to continue on the A81 Garscube Road to join Cowcaddens Road. From here, vehicles will travel to Port Dundas Road to the A804 Dobbies Loan and the diversion will end. Westbound traffic will follow the same diversion, in the opposite direction.

Please note, emergency service vehicles will also be required to use the diversion route.

M8 WOODSIDE VIADUCTS: PARAPET REPLACEMENT WORK COMMENCES 6th OCTOBER

Amey, on behalf of Transport Scotland, are undertaking the next phase of overnight parapet replacement work on the eastbound and westbound M8 Woodside Viaducts at Junction 17. The work will take place from Thursday 6th October to Sunday 9th October 2022, between 10pm and 6am, each night. These roads will re-open outwith the advertised times.

This work requires full overnight carriageway closures of the eastbound M8 at this location on Thursday 6th October and Friday 7th October 2022 and the westbound M8 on Saturday 8th October and Sunday 9th October 2022, with signed diversion routes in operation.

This scheme will install a new and more effective parapet system, ensuring the continued safety and reliability of this busy section of the trunk road network.

  • During the eastbound closures, traffic will be directed to join the southbound M74 to the Kinning Park Junction 1 off-slip road. From here, vehicles will travel via Paisley Road West, Kingston Street and the King George Bridge to the Broomielaw. Then traffic will join the A804 to North Street, St Georges Road and travel on the A804 Phoenix Road and continue via Dobbie’s Loan to the Craighall Roundabout where the diversion will end.
  • During the westbound closures, traffic will exit the M8 at Junction 15 (A803 Springburn) and travel via Castle Street to the A804 Baird Street and continue towards Dobbies Loan. From here, vehicles will continue to A804 Phoenix Road and re-join the westbound M8 via the Junction 17 slip road.

Emergency service vehicles will be provided with access through these works, with manned hold points established to allow this to take place.

Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.

SEPTEMBER 2022

Amey, on behalf of Transport Scotland, are undertaking the next phase of overnight propping works on the M8 Woodside Viaducts on the A804 Phoenix Road, directly below the Viaducts. The propping will take place from Monday 5th September until Saturday 10th September 2022, between 8pm and 6am, each night. These additional restrictions on the A804 Phoenix Road will be removed outwith these times.

This closure is required to erect propping as part of the remedial repairs. Due to the movement of plant and use of cranes for the erection sequence there will be no vehicle access, including no access to emergency service vehicles. All vehicles will be diverted via the local road network.

Traffic will be diverted via St. George’s Road and A81 Garscube Road. Traffic will have access to the westbound M8 at Junction 19.

JULY 2022

M8 WOODSIDE VIADUCT: A81 GARSCUBE ROAD (SOUTH) INVESTIGATION WORKS COMMENCE 1st AUGUST

Amey, on behalf of Transport Scotland, are undertaking a week of utility investigation works on the southbound A81 Garscube Road from 5am on Monday 1st August until 6am on Monday 8th August 2022

The work will take place on the A81 Garscube Road, between St George’s Road and Dobbie’s Loan and will be in place 24/7, with a signed diversion route in operation.

This closure is required to excavate Garscube Road to allow for investigation work into utility services at this location. Due to the depth of the excavation no vehicle access will be possible. Emergency service vehicles and HGVs will also be required to use the diversion route.

Southbound traffic intending to travel via Garscube Road will be diverted via Queen Margaret Drive to Great Western Road. From here vehicles will continue via Cowcaddens Road and can access the eastbound M8 at the A804 Dobbie’s Loan junction. Local business access will be maintained via the M8 and Cowcaddens.

APRIL 2022

M8 WOODSIDE VIADUCT OVERNIGHT PROPPING WORKS IN PLACE FROM WEDNESDAY 27th APRIL

Amey, on behalf of Transport Scotland, are undertaking essential overnight work on the M8 Woodside Viaducts at Junction 16 to 17. In addition to ongoing closures of A804 (see below), there will also be overnight closures on the eastbound A804 Dobbie’s Loan, between 11pm and 6.30am, each night, from Wednesday 27th April to Saturday 30th April and from Monday 2nd May to Saturday 7th May 2022.

Eastbound traffic intending to use Dobbie’s Loan will be directed onto the A81 Garscube Road and from here will follow Cowcaddens Road to Port Dundas Road where it will re-join the eastbound A804. A single lane will provide continued access to the A804 Dobbie’s Loan for westbound traffic.

The latest phase of work to install propping at this structure is currently being undertaken using a series of overnight closures of the A804 Phoenix Road from Monday 25th April until Saturday 30th April, between 8pm and 6:30am, each night. A subsequent phase of work at the same location will take place from Monday 2nd May until Saturday 7th May, again between 8pm and 6.30am each night

For vehicles intending to travel on the A804 Phoenix Road, a signed diversion route will be in operation, with vehicles being diverted via St. George’s Road (eastbound) and A81 Garscube Road (westbound). Access to New City Road and Shamrock Street is being maintained via West Graham Street.

M8 westbound access will be available at M8 Junction 19 via Newton Street. M8 eastbound access will be available via M8 Junction 16.

Please Note: This route will not be open to emergency service vehicles while this work is taking place, and these vehicles are required to follow the signed diversion.

NEXT PHASES OF OVERNIGHT PROPPING WORK ON M8 WOODSIDE VIADUCT COMMENCES MONDAY 25th APRIL

Amey, on behalf of Transport Scotland, are undertaking essential overnight work on the M8 Woodside Viaducts at Junction 16 to 17.

The latest phase of work to install propping at this structure requires a series of overnight closures on the A804 Phoenix Road from Monday 25th April until Saturday 30th April, between 8pm and 6:30am, each night.

A subsequent phase of work at the same location will take place from Monday 2nd May until Saturday 7th May, again between 8pm and 6.30am each night

A signed diversion route will be in operation, with vehicles being diverted via St. George’s Road (eastbound) and A81 Garscube Road (westbound).

Access to New City Road and Shamrock Street is being maintained via West Graham Street.

M8 westbound access will be available at M8 Junction 19 via Newton Street. M8 eastbound access will be available via M8 Junction 16.

Please Note: This route will not be open to emergency service vehicles while this work is taking place, and these vehicles are required to follow the signed diversion.

MARCH 2022

Amey, on behalf of Transport Scotland, are undertaking essential work on the M8 Woodside Viaducts. The latest phase of work to install propping at this structure requires a series of overnight closures of Phoenix Road between St Georges Road and A81 Garscube Road, from Monday 14th March until Saturday 19th March 2022, between 8pm and 6:30am, each night.

A signed diversion route will be in operation, with vehicles being diverted via St George’s Road (eastbound) and A81 Garscube Road (westbound).

M8 westbound access will be available at M8 Junction 19 via Newton Street. M8 eastbound access will be available via M8 Junction 16.

Please Note: This route will not be open to emergency service vehicles while this work is taking place, and these vehicles are required to follow the signed diversion.

Footpath Diversions

To ensure the safety of pedestrians and road workers a series of footpath diversions are in place from Monday 14th February until Friday 11th March 2022. There will be closures of the footpaths adjoining Baird Park; the footway adjacent to A804 Phoenix Road and the underpass footpaths running north and south below Phoenix Road to new City Road.

Signed pedestrian diversions will be in operation while these closures are in place and a footpath diversion map and other key information about this scheme can be found on our website: https://swtrunkroads.scot/m8-woodside-viaducts-j16-j17/

FEBRUARY 2022

OVERNIGHT PROPPING WORK ON M8 WOODSIDE VIADUCT COMMENCES MONDAY 21st FEBRUARY 

Amey, on behalf of Transport Scotland as part of the Network Management Contract for the South West Trunk Road Unit, are undertaking essential work to install propping to the M8 Woodside Viaducts which requires the overnight closure of the A804 Phoenix Road from Monday 21st February until Saturday 26th February 2022, between the hours of 8pm and 6:30am, each night.  

The work will be carried out using a full overnight closure of Phoenix Road between St Georges Road and A81 Garscube Road.  

A signed diversion route will be in operation, with vehicles being diverted via St George’s Road and A81 Garscube Road. M8 westbound access will be available at M8 Junction 19 via Newton Street. M8 eastbound access will be available via M8 Junction 16. 

Please Note: This route will not be open to emergency service vehicles while this work is taking place, and these vehicles are required to follow the signed diversion.  

Temporary pedestrian routes will also be in place - between Monday 14th February and Friday 11th March - to ensure safety of pedestrians, road users and road workers while this construction activity is taking place. 

Footpath Diversions 

To ensure the safety of pedestrians and road workers a series of footpath diversions will be put in place from Monday 14th February until Friday 11th March 2022. There will be closures of the footpaths adjoining Baird Park; the footway adjacent to A804 Phoenix Road and the underpass footpaths running north and south below Phoenix Road to new City Road.  

FOOTPATH DIVERSION MAP

(click image to download PDF)

JANUARY 2022

The installation of temporary propping requires an overnight closure of the A804 Phoenix Road from Monday 24th January until Saturday 29th January 2022, between the hours of 8pm and 6:30am, each night.

The work will be carried out using a full overnight closure of Phoenix Road between St Georges Road and A81 Garscube Road. Temporary pedestrian routes will also be in place to avoid conflict with construction activities between Monday 17th January and Friday 4th February.

A signed diversion route will be in operation, with vehicles being diverted via St George’s Road and A81 Garscube Road. M8 westbound access will be available at M8 Junction 19 via Newton Street. M8 eastbound access will be available via M8 Junction 16.

Please Note: This route will not be open to emergency service vehicles while this work is taking place, and these vehicles are required to follow the signed diversion.

OCTOBER 2021

M8 JUNCTION 18 EASTBOUND ON-SLIP ROAD TO RE-OPEN SUNDAY  24th OCTOBER 2021

The M8 Junction 18 eastbound on-slip road will re-open from 6:30am on Sunday 24th October 2021. This is the latest phase of traffic management related to the ongoing maintenance work taking place on the M8 at Woodside Viaducts from Junction 16 to Junction 17.

The eastbound Junction 18 on-slip will be reduced in length and a new road marking layout and temporary speed restriction will be in place to allow a merge with the M8 eastbound mainline. Existing traffic management will remain the same at other locations on the M8 Junctions 16 to 17, and adjacent roads.

Please note, traffic flows at peak times are likely to increase at Junction 18 once this slip is re-opened and road users are advised to plan the time of their journey accordingly or seek an alternative route if possible.

This traffic management will assist with the safe excavation and installation of the specialist temporary bridge propping system below M8 Woodside Viaducts. The initial design phase of the bridge propping system is nearing completion, and the preparations for the installation of the temporary propping are well underway.

The permanent bridge repair continues to undergo a detailed design review and our team is carrying out enhanced engagement with stakeholders to minimise disruption within the area. Each stage of the programme will be rolled out soon as it is agreed, to reduce the overall length of the repair and maximise efficiency by ensuring progressive stages of the work overlap.

AUGUST 2021

An initial trial site excavation has been completed, which was undertaken to expose one of the buried foundations and allowed for preparatory concreting works necessary to support the installation of temporary bridge props. The trial excavation has provided our engineers with valuable information on the below ground conditions, which will help inform further design and construction work at the subsequent bridge piers.

The first stage of the construction programme involves the excavation, piling or construction of high-level support works around the existing bridge columns. This work commenced on Sunday 15th August 2021

To facilitate the first stage of these programmed works, a three-phase traffic management scheme commenced, 24/7, along the A804 Phoenix Road:

  • Traffic Management Phase 1a was installed during the evening of Sunday 15th August 2021 and required nearside lane closures on both the eastbound and westbound A804, Phoenix Road, between Garscube Roundabout and the M8 West on-slip road for Junction 17. Left-only access was put in place to New City Road. A signed diversion route operated via New City Road, Shamrock Street, and Scott Street. This diversion continued onto West Graham Street and Garscube Road.

  • Traffic Management Phase 1b will be installed during the evening of Sunday 22nd August 2021 with a lane restriction in place on the M8 Junction 17 West on-slip road, situated beyond the right-hand turn from the A804, Phoenix Road. This is to allow for excavation works under the viaduct.

  • Traffic Management Phase 1c dates will be confirmed nearer the time with a nearside lane closure on the A804, Dobbie’s Loan for access to the M8 Junction 16 Eastbound on-slip road.

Please note, each traffic management scheme will be an extension of what is already in place. No traffic management measures will be removed prior to the next traffic management scheme commencing.

Public access will be maintained for the pedestrian underpass beneath Phoenix Road, which will be accessible via the construction of a temporary ramp. Closed pedestrian access will be well signposted at the site with alternative routes.

Future construction stages of the project will see the installation of the bridge propping system and jacking of the structures to complete repairs to the crossheads. These future stages are undergoing a detailed design review and our team is carrying out enhanced engagement with stakeholders to minimise disruption within the area. Each stage of the programme will be rolled out soon as it is agreed, to reduce the overall length of the repair and maximise efficiency by ensuring progressive stages of the work overlap.